
Vol.
23, No. 5, Sept. 4,2003
Status of major construction projects on
campus:
- Central Campus
Chilled Water Project Construction
of the new 20,000-ton chilled water plant is about 60 percent complete. Traffic
rerouting and street closures will continue on Gregory and Peabody drives
and later on College Court between Virginia Drive and Lincoln Avenue as crews
install piping around campus. The intersection of Peabody Drive and Dorner
Drive is expected to reopen Sept. 8. Traffic will be rerouted and reduced
to one lane each way on Green Street between Goodwin and Lincoln avenues until
late October while crews lay piping for Loomis Lab. During September, crews
will remove a sidewalk on the east side of Henry Administration Building temporarily
while they are working in that area. Oak Street will reopen temporarily for
the Sept. 6 football game but will not be completed until later in the month.
 |
| Photo
by Bill Wiegand |
| Moving up
Construction
is progressing on the new parking garage located on the
north side of campus, east of the Beckman Institute. Contractors
are working on the fourth level of the six-level parking
deck, scheduled for completion in February. |
|
|
- Campustown
Infrastructure Reconstruction and Streetscape Project (City of Champaign)
Sixth Street
was reduced to one lane and diagonal parking installed on the west side from
Healey Street to John Street during the summer. Mid-block pedestrian crossings,
benches and bike racks also were placed along Sixth Street, new street lighting
installed in the 600 block of John and new sewers installed between Green
and John streets. The City of Champaign is developing an improvement plan
for the entire University District and seeking funding to continue with the
project. The city also is negotiating a proposal for a development with 12
stories of apartments, two stories of commercial space and a 400-space parking
deck for the city parking lot and vacated Wendy’s restaurant property
at the corner of Green and Sixth streets.
- Abbott Power
Plant A $60
million expansion of Abbott Power Plant is targeted for completion in October.
Construction of the cogeneration building is nearing completion; the project
also includes installation and commissioning of gas turbine generators, heat
recovery steam generators and water treatment equipment.
- Bardeen Quadrangle
Improvement work on the engineering quad and Boneyard Creek between Green
Street and Springfield Avenue is nearly complete but planting will continue
into November. Improvements to the area include new walkways, decorative paving
and stone retaining walls.
 |
| Photo
by Bill Wiegand |
| Getting there
A
view from the intersection of Mathews Avenue and Stoughton
Street shows progress of construction on the Thomas M.
Siebel Center for Computer Science. Plans call for the
building to be completed in October. |
|
|
- North Campus
Parking Deck
Contractors are working on the fourth level of the six-level parking deck
near the intersection of University Avenue and Goodwin Avenue. The $26 million
project, scheduled for completion in February, will include parking for 1,600
cars and 20,000 square feet of retail space.
- U.S. 150
Springfield Avenue/U.S. 150 has been resurfaced from Prairie Street to Wright
Street and north on Wright Street to University Avenue, Champaign. Turn lanes
will be installed at U.S. 150 and Goodwin Avenue in Urbana.
- McKinley Health
Center McKinley
is undergoing a $3.7 million facelift that includes new partitions, flooring
and ceilings as well as new electrical, mechanical and telecomunnications
systems. The remodeling will continue through May 2004.
- Thomas M. Siebel
Center for Computer Science The
$80 million project, which will include 250,000 square feet of classrooms,
offices and computer laboratories, should be substantially finished in October.
The site is east of Newmark Laboratory near Goodwin Avenue and White Street.
n National Center for Supercomputing Applications Construction began in late
August on a 127,000 gross-square-foot building that will include offices,
research labs and conference and training facilities. The $30 million project
is targeted for completion in July 2005. The supercomputing facility will
be north of the Siebel Center.
- IMPE and CRCE
Expansion The
$77 million expansion and renovation of Campus Recreation facilities will
begin in September. CRCE will be closed for renovations until August 2004.
After CRCE has reopened, major construction will begin at IMPE and will continue
until Fall 2006.
- Upcoming projects
In December, construction is expected to begin on the $73.5 million Institute
for Genomic Biology, near Goodwin Avenue and Gregory Street, and the $8.5
million Doris Kelley Christopher Hall/Family Resiliency Center, near Lincoln
Avenue and Nevada Street.
Back
to Inside Illinois Index