|
 |
 |

PUBLICATIONS
Inside
Illinois
Vol.
21, No. 19, May 2, 2002
Construction
in Campustown continues on schedule
By Sharita
Forrest, Assistant Editor
(217) 244-1072; slforres@illinois.edu
 |
|
Photo
by Bill Wiegand
|
|
Campustown
facelift Construction
crews continue their work on Green Street, reducing it from
two lanes to one lane in each direction with a center turn
lane. Portions of Green Street will remain closed to vehicular
traffic until July or August when new traffic lights have
been installed and are operational, city officials said.
|
|
Street reconstruction
in campustown is a little ahead of schedule although much remains to
be done, Champaign city officials reported at an April 24 progress meeting.
The current phase of the $5.5 million construction project is about
one-third done, with Aug. 23 as the target date for completion, Louis
Braghini, project manager for the city of Champaign, said at the meeting.
Street paving has been completed in the 600 block of Green Street and
should be finished soon in the 500 block. Crews are now installing storm
sewers in the 300 and 400 blocks of Green Street.
However, portions of Green Street will remain closed to vehicular traffic
until traffic lights have been installed and are operational, which
will be well into July or August, said Rick Marley, assistant city engineer.
When construction is complete, Green Street will become one lane in
each direction with a center turn lane.
Braghini said construction crews and city officials are doing their
best to move the project along quickly and minimize the economic impact
on Campustown businesses.
 |
|
Photo
by Bill Wiegand
|
|
Making
progress
Much underground work remains to be done on Green Street,
such as reconstruction of storm and sanitary sewers. The
current phase of the reconstruction and streetscape project
should be "substantially complete" by Aug. 23.
|
|
The changes in traffic
circulation patterns on Campustown streets have prompted some complaints
from motorists about congestion at the Pennsylvania Avenue-Sixth Street
intersection and about the difficulty of northbound egress since Wright
Street was closed to automobile traffic between Daniel and Green streets.
Acknowledging that the new traffic circulation plan can be inconvenient
for motorists trying to travel north out of campus, Marley said the
traffic pattern is specifically designed to enhance pedestrian safety
by diverting automobiles away from high-volume pedestrian areas.
On May 1, university officials formally requested that Champaign-Urbana
Urbanized Area Transportation Study (CUATS) officials examine how the
intersections at Sixth Street and Pennsylvania Avenue and Sixth Street
and Armory Avenue have been affected by the new circulation plan, said
Gary Biehl, management engineer, UI Operation and Maintenance.
In late May, the city expects to receive approval from the Illinois
Department of Transportation for planned improvements at the Wright
Street-Springfield Avenue intersection, which will facilitate two-way
bus traffic on Wright Street north of Healey Street. Construction is
expected to begin in July and be finished by the end of 2002.
In spring 2003, work will begin on the north-south Campustown streets.
Seasoned Campustown motorists may not be surprised to learn that pedestrians
are causing headaches for the projects construction crews. Wayward
walkers are frequently circumnavigating construction barricades and
tramping through freshly poured concrete, city officials said.
"As we all know, students walk wherever they want to, and thats
happened to us many times," Braghini said.
|
 |
 |
|